  1. way: In the BMS Core Studio open the menu Extensions and click [Live] Holiday definitions - the list of holidays stored in the system will be shown.

    The holidays can be entered manually in the list (right mouse click) or imported from an Excel file. Also the export to Excel is possible.
    For import or export please click the icon in the menu bar .

  2. way: In the BMS Web Manager open the module Scheduler and click the symbol  on the left side. The list of holidays actually stored in the system will be shown again.
    New holidays can be entered in the list after clicking the botton .
    For import or export to Excel click the buttons .


The setup of holidays are stored in the file nxaHolidays.40.dat - click here for details.

How to do the holiday settings?

All events have a setting how to treat holidays. 

To setup, choose one of the following:

  • Ignore: when the event is executed, it doesn't matter if the current day is a holiday currholiday or not - so holidays are ignored.
  • Include: the event is executed only on holidays.
  • Exclude: the event is executed only when the day of execution is no holiday.